August & September Photos recital hall north courtyard standing at the fireplace panoramic of the lobby, office, waiting area and entrance to recital hall. looking west from the waiting room west wall northwest corner 9/4/24 - Trusses are going on! west wall northwest corner view from the south view from the east The first truss! August 26 - Studio walls going up west wall Slab pour on Aug 12 June & July Photos Mid July - Install subgrade utilities Footprint of new building 7/22/24 Hard workers! Mid July - install below grade utilities Street closure Southwest corner July - recital hall - backfill to subgrade July - waterproof drain mat July - waterproof drain mat Early July - set and form walls North studio wing Recital hall Early July - set and form walls South wall West entrance South wall North studio wing East wall - Front entrance North outdoor classroom June - Form and place walls Inside school at waiting area June - Form and Place footings Northwest corner Northeast corner North studio wing Southeast corner and main entrance West entrance May Photos East view of excavation Southeast view North entrance to property South view of property Setting up the fencing North entrance to Smith Fields Laying ground mat and crush for parking lot Groundbreaking April 19, 2024